36 men can complete a piece of work in 18 days. How many days will 27 men take to complete the same work?

Please select one of the options to reveal the correct answer.

Similar MCQs

Which is the largest human made tank in Assam? What percentage of India's total eri silk production comes from the Bodoland Territorial Region (BTR)? Choose the correct complex sentence for the following simple sentence: “She went to the market.” Who was the Ahom king who received the title of Gajapati? A number is as much greater than 22 as it is less than 72. What is the number?